EV Charging for Body Corporates: Approvals, Costs & Load Management

Residents are buying electric vehicles, and committees are getting the same three questions: who has to approve chargers, who pays, and will the building’s power cope? This guide answers all three for body corporates and strata managers in Brisbane and South East Queensland, so your committee can make a decision with the right information.

Quick summary: check what your by-laws and the BCCM rules require → measure the building’s spare electrical capacity → choose a charging model (individual chargers or a shared system) with load management → agree how electricity is metered and billed → approve and roll out in stages.

Who approves EV chargers in a Queensland body corporate?

Most Queensland schemes run under the Body Corporate and Community Management Act 1997 (BCCM Act) and its regulation modules. The Queensland Government’s Office of the Commissioner for Body Corporate and Community Management has published an EV fact sheet that sets out two common situations:

  • The body corporate installs chargers on common property (for example shared chargers in a visitor or common car park). This is treated as an improvement to common property. Depending on the cost, the committee may be able to approve it, or it may need a resolution at a general meeting.
  • An owner wants their own charger connected to common property or common electrical infrastructure. The owner needs body corporate approval. Under the Standard Module, the committee can approve it if the total cost is under $3,000, it doesn’t spoil the look of the building, and it is unlikely to cause the owner to breach their duties. Otherwise it goes to a general meeting as an ordinary resolution.

The fact sheet also reminds committees that they must act reasonably when deciding on applications, that the owner is normally responsible for maintaining their charger, and that approvals can carry conditions. Some buildings also consider exclusive use by-laws, leases or licences for parking spaces with chargers, and most committees speak to their building insurer before approving anything. Rules differ between regulation modules and schemes, so check your own by-laws with your strata manager, and get legal advice on any new by-law wording.

What we provide for the approval: a written capacity report and a fixed quote that your committee can table at a meeting, so owners vote on real numbers rather than guesses.

Two ways to set up EV charging in a building

1. Individual chargers on each lot’s supply

Each owner installs a charger in their own car space, wired from their own unit meter or sub-board. Billing is simple because the power goes on the owner’s own account, but cable runs from units to the car park can be long and expensive, and without a plan the building can run out of capacity after the first few installs.

2. A shared “backbone” from common property

The body corporate installs one EV distribution board and cabling route (the backbone), with load management, and owners connect chargers to it as they need them. Electricity is recovered through sub-metering or app-based billing. It costs more up front but is usually cheaper per charger, keeps the car park tidy and protects the building’s supply.

Many buildings choose the backbone approach and roll it out in stages: the infrastructure first, then chargers as residents buy EVs.

Will the building’s power cope?

A typical apartment car park charger is 7 kW, which draws about 32 amps on a single phase. Ten of those charging at full power at the same time is around 320 amps – more spare capacity than many older buildings have. That’s why capacity is the first thing to check, not the last.

We measure the building’s real peak demand by data logging the main switchboard and compare it with what the supply and main switchboard can safely carry. Our step-by-step guide, How much power does your building need for EV chargers?, explains the calculation with a worked example.

Load management: more chargers without a bigger supply

Load management (also called dynamic load balancing) monitors the building’s total demand and shares the available spare capacity between the chargers in use. When the building is busy – for example on a hot evening with air conditioning running – each car charges more slowly; overnight, when demand drops, cars charge at full speed.

For most strata buildings this is the single biggest saving. It often means many more chargers can be supported on the existing supply, and a switchboard or supply upgrade can be avoided or delayed.

What affects the cost?

Every building is different, so we quote after an assessment. The main cost drivers are:

  • Spare capacity: whether the existing supply and main switchboard can carry the load, or a power capacity upgrade or new main switchboard is needed
  • Distance and cable routes: how far the car park is from the main switchboard and how cables can be run through the building
  • Number of chargers and their size (7 kW single phase or 11–22 kW three phase)
  • Load management and billing system chosen
  • Approvals: any supply change needs Energex approval, and metering changes involve the energy retailer
  • Fire and building requirements raised by your insurer or fire safety adviser

Measuring first avoids the two most expensive mistakes: upgrading a supply that didn’t need it, or installing chargers that the building can’t power.

Billing residents for the electricity they use

If chargers run from common property, the body corporate needs a fair way to recover the cost of electricity. Common options are individual sub-meters on each charger, or networked chargers with app or card billing. The BCCM fact sheet suggests committees consider how electricity will be metered and charged before approving chargers, whether a supply of services agreement is needed, and making sure the arrangement doesn’t amount to the body corporate running a business. Your strata manager can advise on the right structure for your scheme.

A step-by-step plan for your committee

  1. Survey residents to see how many owners have or plan to buy an EV in the next few years.
  2. Check the rules: your by-laws, the BCCM fact sheet and your building insurer’s requirements.
  3. Book a capacity assessment – data logging of the main switchboard and a site inspection.
  4. Choose the charging model (individual or shared backbone) and load management.
  5. Table the report and quote at a committee or general meeting for approval.
  6. Install in stages – backbone first, then chargers as residents request them.

If the assessment shows the main switchboard is old or at capacity, our body corporate switchboard upgrade guide explains the upgrade process and how we keep residents on power during the changeover.

Frequently asked questions

Can a body corporate refuse an owner’s request for an EV charger?

The body corporate must act reasonably when it decides an application, and approvals can come with conditions such as who maintains the charger and how electricity is paid for. If an owner disagrees with a decision, the Office of the Commissioner for Body Corporate and Community Management offers information and dispute resolution.

Does the committee or a general meeting approve EV chargers?

It depends on who is installing the charger and the cost. Under the Standard Module, the committee can approve an owner’s charger connected to common property if it costs under $3,000 and meets the other conditions; otherwise it needs a general meeting. Larger body corporate projects may also need a general meeting resolution. Your strata manager can confirm what applies to your scheme.

How many EV chargers can our building support?

It depends on your spare capacity and whether you use load management. The only reliable way to know is to measure the building’s actual peak demand with data logging. See our EV capacity guide for strata buildings.

Do we need to upgrade the switchboard for EV charging?

Not always. With load management many buildings can add chargers on their existing supply. An upgrade is usually needed when the main switchboard is old, has no space for new circuits, or the measured spare capacity is too small for the number of chargers planned.

Can you install the chargers as well?

Yes. We assess capacity, upgrade the switchboard if needed, and install and commission the chargers and load management. See our EV charger installations page.

This guide is general information, not legal advice. Source: Queensland Government, Office of the Commissioner for Body Corporate and Community Management – “Electric vehicles” fact sheet (January 2026).

Book an EV capacity assessment for your building

Get the numbers your committee needs before anyone votes. We’ll data log your main switchboard, inspect the car park and give you a written report and quote to table at your next meeting. Prefer to talk? Call 1300 788 455.









    ⓘ Need someone to help design a switchboard solution, organise the manufacturing, coordination and installation? That’s us.

    Upload file (.jpg, .png, .doc, .pdf up to 3MB)

    *mandatory fields

    Call 1300 788 455