Planning a Switchboard Shutdown: Minimising Downtime for Businesses & Strata

Replacing or upgrading a main switchboard almost always means a planned power outage. Done well, residents and tenants barely notice. Done badly, it means lost trade, angry residents and spoiled stock. Here is how to plan a shutdown that keeps downtime to a minimum.

Call 1300 788 455 or get a fixed quote.

1. Plan the timing

  • Choose a low-impact window: overnight, a weekend, or a business shutdown period such as Christmas.
  • Allow for Energex and metering bookings, which have their own lead times. See Energex applications explained.
  • For custom-built boards, confirm the delivery date before locking in the outage.

2. Do as much as possible before the outage

Good planning moves work out of the shutdown window. That includes pre-wiring the new board, running new cables, labelling every circuit and preparing a step-by-step changeover plan. The power should only be off for the final connection and testing.

3. Arrange temporary power where needed

Lifts, fire systems, refrigeration, servers and medical equipment may need generators or temporary supplies. Identify these loads early and agree how each will be handled.

4. Notify everyone

  • Strata: committee approval, then written notices to residents with dates, times and what to expect (lifts, garage doors, fridges, medical equipment).
  • Commercial: tenants, IT, security and alarm monitoring, and any contractors on site.
  • Remind people to switch off sensitive equipment before the outage.

5. On the day

  • Confirm Energex and metering attendance.
  • Isolate, change over, test and re-energise in the planned order.
  • Check lifts, fire panels, pumps and critical equipment as soon as power is restored.
  • Collect the certificate of testing and safety and updated circuit schedules.

Shutdown checklist

  1. Inspection and scope agreed
  2. Board ordered and delivery date confirmed
  3. Energex application and EWR lodged
  4. Outage window approved
  5. Critical loads and temporary power planned
  6. Notices sent at least a week before
  7. Pre-work completed
  8. Changeover, testing and handover

We plan and run shutdowns for body corporates, commercial buildings and factories and warehouses across Brisbane and SEQ. See also the Body Corporate Switchboard Upgrade Guide.

Frequently asked questions

How long will the power be off during a switchboard upgrade?

It depends on the job. With good pre-work, many changeovers take a few hours. Large main switchboards can take longer, which is why they are often done overnight or on weekends.

Can the shutdown be done after hours?

Yes. We regularly schedule shutdowns overnight, on weekends or during business closures.

How much notice should residents get?

At least a week is good practice, with a reminder a day or two before.

What happens to lifts and fire systems?

They are identified in planning. Some need temporary power, and all are checked as soon as power is restored.

Planning a switchboard shutdown?

Tell us about your building and we’ll plan the outage, paperwork and changeover with a fixed quote. Prefer to talk? Call 1300 788 455.









    ⓘ Need someone to help design a switchboard solution, organise the manufacturing, coordination and installation? That’s us.

    Upload file (.jpg, .png, .doc, .pdf up to 3MB)

    *mandatory fields

    Call 1300 788 455