If you are adding air-conditioning, an EV charger, a battery or new equipment, you may have been told you need “three phase”. Before you spend money on a supply upgrade, it helps to understand what single and three phase power are, when three phase genuinely helps, and when a smarter single-phase setup will do.
Call 1300 788 455 or get a fixed quote.
Single phase power arrives on one active conductor plus neutral at 230 V. Most older Brisbane homes are single phase, and many have a main fuse that limits how much current the whole property can draw at once.
Three phase power arrives on three active conductors plus neutral, giving 400 V between phases. It provides roughly three times the capacity of a single-phase supply of the same rating per phase, and it can run three-phase motors and large equipment directly.
| Single phase | Three phase | |
|---|---|---|
| Voltage | 230 V | 230 V per phase, 400 V between phases |
| Typical use | Most homes and small shops | Larger homes, units with big loads, commercial and industrial sites |
| Large equipment | Limited | Runs three-phase motors, compressors and fast EV chargers |
| Upgrade needed? | — | Energex supply upgrade and a switchboard able to take three phases |
Usually not. Most household appliances, including air-conditioners and induction cooktops, run happily on single phase. Three phase is worth considering when:
Before upgrading, a licensed electrician should check the actual load. Energy data logging shows what the property really uses, and load management can sometimes avoid the upgrade.
Most commercial and industrial sites and nearly all apartment buildings already have three-phase supply. The question there is usually whether the supply and main switchboard have enough capacity per phase, and whether the load is balanced across the phases. See power capacity upgrades.
Costs depend heavily on whether three phase is available in your street and how far the mains run. We give a fixed quote after inspection. Read more about our three phase power service.
No. You pay for the energy you use, not the number of phases. A three-phase connection may have a different daily supply charge depending on your retailer and tariff.
Not usually. A 7 kW single-phase charger suits most homes. Three phase is only needed for faster 11–22 kW chargers or where the property is already near its limit.
Look at the main switch on your switchboard. A three-pole main switch, or three main fuses at the meter, usually means three phase. An electrician can confirm it.
The on-site work is often one to two days, but the full process depends on Energex and metering timeframes.
Tell us what you’re planning to add and we’ll check your supply and give you a fixed quote. Prefer to talk? Call 1300 788 455.