Suburb: Carindale, QLD 4152
Size: 12 Townhouses
Building: Residential Unit Block
A townhouse complex sub mains was overloading every 2 weeks for two townhouses causing power loss to both units. We data logged the power consumption discovering that the townhouses were drawing far too much current during peak usage times by 26amps. This resulted in having to upgrade the consumer sub mains to both townhouses which rectified the problem.